Sunday, November 18, 2012

Day 19 - A Toilet

Nothing further construction wise happened last week. I spoke to our SS on Thursday to ask when the piers and plumbing were going to happen. The peg out report had still not been received, so nothing could happen.  Piers were being pushed back to next Tuesday (20th November) and possibly a slab a week after that.  To say I was furious was an understatement.   A slab was promised within 2 weeks of the file going to the SS, and now we are are over the 2 weeks and the block has been cut, nothing more.

Friday afternoon my mother-in-law went past the block in the afternoon and noticed that the portaloo had been delivered


I guess it is something. 