Day 1 - 31/10/12 - Receive phone call from SS
Day 3 - 02/11/12 - Meet with SS on site
Day 6 - 05/11/12 - Site peg out booked - didn't happen
Day 7 - 06/11/12 - Rawson sign on block. No pegs.
Day 9 - 08/11/12 - Site peg out
Day 14 - 13/11/12 - Site cut.
Day 17 - 16/11/12 - Portaloo
Day 20 - 19/11/12 - Piers
Day 21 - 20/11/12 - Plumbing
Day 22 - 21/11/12 - Slab form
Day 23 - 22/11/12 - Slab form
Day 24 - 23/11/12 - Slab form
Day 28 - 27/11/12 - Slab pour
Day 29 - 28/11/12 - Lower frames and steels delivered
Day 29 - 28/11/12 - Sediment Control Fence and skip bin delivered
Day 30 - 29/11/12 - Termite barrier installed.
Day 30 - 29/11/12 - Windows and additional framing delivered
Day 31 - 30/11/12 - First progress claim received
Day 32 - 01/12/12 - Lower floor frames erected.
Day 35 - 04/12/12 - Some windows and joists installed
Day 36 - 05/12/12 - Remaining floor joists, steels installed for lower storey. Upper frames
Day 37 - 06/12/12 - Roof trusses
Day 38 - 07/12/12 - Protect a Window painted on all windows to stop scratching
Day 43 - 12/12/12 - Framing continued
Day 44 - 13/12/12 - Framing complete
Day 45 - 14/12/12 - Frame invoice received
Day 46 - 15/12/12 - Tile appointment
Day 48 - 17/12/12 - Plumbers continue. Water tap and preliminary connection to block
Day 67 - 05/12/12 - Water meter installed. Still no water
Day 70 - 08/01/13 - Bricks finally arrive.
Day 76 - 14/01/13 - Water finally connected. Sand delivered
Day 84 - 22/01/13 - Bricklayers arrive
Day 93 - 30/01/13 - Scaffold erected, second delivery of bricks
Day 94 - 31/01/13 - Bricklayers return to start second storey
Day 104 - 11/02/13 - Scaffolding raised for roof to start
Day 105 - 12/02/13 - Plumbing rough-in started
Day 106 - 13/02/13 - Fascia and gutter installed
Day 106 - 13/02/13 - Plumbing rough-in completed
Day 111 - 18/02/13 - Roof rail installed. Roof tiles delivered
Day 112 - 19/02/13 - Roof started
Day 112 - 19/02/13 - Third delivery of bricks received.
Day 119 - 26/02/13 - Bricks finish
Day 119 - 26/02/13 - Top roof completed
Day 120 - 27/02/13 - Roof rail taken down
Day 120 - 27/02/13 - Exhaust vents installed on roof
Day 121 - 28/02/13 - Brick invoice received.
Day 125 - 04/03/13 - Carpentry started - internal works only.
Day 126 - 05/03/13 - Gutter Guard installed
Day 127 - 06/03/13 - Scaffolding heights changed
Day 130 - 09/03/13 - External carpentry started
Day 131 - 10/03/13 - Bricks cleaned
Day 134 - 13/03/13 - External carpentry completed
Day 135 - 14/03/13 - Waterproofing of bathrooms and laundry
Day 136 - 15/03/13 - External painting starts
Day 137 - 16/03/13 - Second visit for brick cleaner
Day 140 - 19/03/13 - Scaffolding removed
Day 140 - 19/03/13 - Sliding door glass installed - not the type of doors that we wanted
Day 143 - 21/03/13 - Sliding doors to be changed to stacker doors. New doors ordered.
Day 143 - 21/03/13 - Fascia and gutter installed garage and alfresco
Day 144 - 22/03/13 - Roof rail installed garage and alfresco
Day 144 - 22/03/13 - Garage roof completed
Day 145 - 23/03/13 - Brick Clean #3
Day 147 - 25/03/13 - Electrical rough in
Day 147 - 25/03/13 - Alfresco roof started
Day 148 - 26/03/13 - Electrical rough in completed
Day 148 - 26/03/13 - Air Conditioning rough in started
Day 148 - 26/03/13 - Alfresco roof completed
Day 148 - 26/03/13 - Site clean
Day 149 - 27/03/13 - Air Conditioning rough in completed
Day 150 - 28/03/13 - Alfresco eaves and main bedroom balcony deck completed
Day 154 - 02/04/13 - Gyprock delivered
Day 155 - 03/04/13 - Insulation delivered
Day 157 - 05/04/13 - Gutter guard to garage and alfresco roof''s installed
Day 157 - 05/04/13 - Insulation installed.
Day 161 - 09/04/13 - Gyprock started.
Day 163 - 11/04/13 - Electrical mains and power pole installed
Day 170 - 19/04/13 - Internal linings invoice received.
Day 171 - 20/04/13 - Gyprock completed
Day 173 - 22/04/13 - Stairs installed
Day 174 - 23/04/13 - Carpentry fix out started
Day 177 - 26/04/13 - Locked up
Day 178 - 27/04/13 - Stacker doors installed
Day 187 - 06/05/13 - Garage door installed
Day 190 - 09/05/13 - Carpentry fix out completed - front door installed
Day 190 - 09/05/13 - Balcony Handrail installed
Day 194 - 13/05/13 - Kitchen and vanities installed
Day 195 - 14/05/13 - Tank installed
Day 197 - 16/05/13 - Door handle installed
Day 199 - 18/05/13 - Gabion walls
Day 201 - 20/05/13 - Internal painting started
Day 202 - 21/05/13 - Stone benchtops and vanity tops installed
Day 203 - 22/05/13 - Tiling started
Day 214 - 02/06/13 - Tiling finished
Day 216 - 04/06/13 - All scaffolding removed.
Day 216 - 04/06/13 - Shower screens and wardrobes measured
Day 217 - 05/06/13 - Site Fence removed
Day 223 - 11/06/13 - Plumbing fit off started
Day 226 - 14/06/13 - Electrical fit off started
Day 226 - 14/06/13 - Air Conditioning fit off
Day 229 - 17/06/13 - Glass splashback ordered
Day 230 - 18/06/13 - Shower screens and wardrobes installed.
Day 238 - 26/06/13 - Painters finish
Day 239 - 27/06/13 - Carpentry fit off
Day 238 - 27/06/13 - Flyscreens and screen doors fitted
Day 240 - 28/06/13 -Carpentry fit off
Day 243 - 01/07/13 - Council final inspection
Day 243 - 01/07/13 - Practical Completion invoice faxed to bank.
Day 243 - 01/07/13 - SS walkthrough
Day 244 - 02/07/13 - Painters back to start touchups
Day 246 - 04/07/13 - Stacker door flyscreen frames installed
Day 247 - 05/07/13 - Practical Completion Inspection
Day 247 - 05/07/13 - Final bank valuation
Day 248 - 06/07/13 - Driveway works commence
Day 251 - 09/07/13 - Final Occupation Certificate Issued
Day 252 - 10/07/13 - Final cheque available to be collected from CUA
Day 253 - 11/07/13 - Handover
Hi Matt and Jen,
ReplyDeleteMy husband and I are building a Ferbside 38 with Rawson as you have done. We are finding your blog very helpful and insightful. We were wondering whether it would be possible to have a walk through your house and talk to you about the changes you have made from the original plan, as we are making changes ourselves. We look forward to hearing from you.