We have had action at the house,  but I have not had the time to blog it. So here is a little taste of the progress

Tuesday last week we had a totally empty bin. By Wednesday afternoon, it was overflowing


Wednesday the toilets were installed.  


I love that they have left the toilet seats off. Maybe it discourages the tradies from using the spanking new toilet.

The rain head shower was installed in the 5th bedroom ensuite


My biggest excitement was that the dishwasher, mircowave and oven were also installed.






Friday was air conditioning and electrical fit off.  Love the fact that Daikin Air Conditioning is a standard inclusion with Rawson.


Yesterday I met on site with our SS and went over all the things that are scheduled over the next couple of weeks before we handover.

Shower screens and wardrobes were booked in for Thursday and Friday - they are at the house today.

Electrical fit off is being finished today.

Painters are back next week - hopefully they will be finished in four days.   Then it is the race to the finish line.  Handover date 5th July.